Q. A, B and C can do a piece of work in 36, 54 and 72 days respectively. they started the work but A left 8 days befire the completion of the work while B left 12 days before the completion. The number of days for which C worked is  ?

Question ID: 5835
  1. 4
  2. 8
  3. 12
  4. 24