Q. The digging work of the DMRC on the Adohini-Andheriamore stretch requires Twenty-four men to complete the work in sixteen days. As a part of the task if DMRC were to hire Thirty-two women, they can complete the same work in twenty-four days. Sixteen men and sixteen women started working and worked for twelve days. Due to time bound schedule the work had to be completed in remaining 2 days, for which how many more men are to be employed?

Question ID: 19122
  1. 48
  2. 24
  3. 36
  4. 16